American Boulevard - Owner: City of Bloomington
- Engineer: City of Bloomington
- $4,000,000.00 road reconstruction project done in multiple phases under traffic.
- All removals and demolition debris recycled onsite to limit truck traffic to and from the project.
84th and East Bush Lake Road - Owner: City of Bloomington
- Engineer: City of Bloomington
- $4,000,000.00 road reconstruction
project done in multiple phases under traffic.
- Owner realized substantial
savings due to our value engineering proposals.
Taxiway CD Reconstruction
Phase 3 - Owner: Metropolitan Airports Commission
- Engineer:
TKDA
- $6,000,000.00 reconstruction of taxiway including concrete pavement.
- With careful planning, MSI was able to meet the aggressive schedule set by the Onwer.
- All concrete was recycled onsite.
Runway 12R 30L Segment 2 Reconstruction - Owner: Metropolitan Airports Commission
- Customer: Progressive Contractors,
Inc.
- Working around the clock, MSI assited PCI in demolishing and rebuilding one of the main
runways at MSP in a short time frame that had to be met.
Max
Steininger, Inc. 3080 Lexington Avenue S. Eagan, MN 55121 phone
651-454-6620 fax 651-454-6716 maxgrading.com
|